Completed MNPS Construction Projects

  • Antioch High School

    Classroom Addition

    This project included a 20 classroom addition to Antioch High School. This project allowed the classes currently in portable buildings on the campus to be moved inside the building.

    Project Details
    • Location: 1900 Hobson Pike
    • Total project square footage: 39,825 SF
    • Allocated funding: $6,900,000
    • Architect: JJCA
    • Contractor: SouthLand Constructors
    • Completed: August 2018
    • Construction Updates

     

 


 

  • Hillsboro High School

    Renovation & Addition

    The project includes a full renovation of Hillsboro High School plus an addition to the school to expand the space to meet the current school attendance and academic needs as well as planning for future growth. Interior improvements include LED lighting, flexible collaborative furniture, and new technology.
    There will be a new library, cafeteria and kitchen, art spaces, outdoor courtyard areas, community room, and enrollment center. The school will be reorganized with Administrative offices and CTE spaces central to each Academy.

    Project Details

 


  • Eagle View Elementary

    New Elementary School

    This is a brand new elementary school planned for a capacity of 800 students. The school is being constructed on Eagle View Blvd in Antioch. This school will be designed to achieve LEED Silver accreditation once completed.

    Project Details
    • Location - 1470 Eagle View Blvd
    • Total project square footage - 99,615 SF
    • Allocated funding - $19,000,000
    • Architect - EOA Architects
    • Contractor - Orion Building Corporation
  • Library
  • Exterior
  • Gym

 


  • Crieve Hall Elementary

    Classroom Addition

    This project will include an addition for 8 classrooms. The project will also feature construction of a new library. The cafeteria will also be expanded. Other support functions will also be added to the building.

    Project Details
    • Location - 498 Hogan Rd
    • Total project square footage - 18,127 SF
    • Allocated Funding - $5,500,000
    • Architect - Goodwyn Mills Cawood
    • Contractor - Orion Building Corporation
  • Library
  • Classroom
  • Hallway

 

 


  • East Nashville Magnet

    Stadium Upgrade

    This project will add new bleachers to the football/track facility. A new building will also be constructed with concession stand, press box, restrooms, and ticket booth. A PA system and score board will also be added. The final component of this project is site work including fencing, sidewalks, and ramps.

    Project Details
    • Location - 110 Gallatin Ave
    • Total project square footage - 2,896 SF
    • Allocated funding - $ 2,750,000
    • Architect - EOA Architects
    • Contractor - Romach General Contractors

 

 


  • Glencliff High School

    Track Facility Renovation

    This project consists of the construction of a new 400 meter track. The concession stand and restroom building will also be torn down and constructed a new. The new building will also include a ticket booth and alumni room. The final component to this project is sitework including fencing, sidewalks, stairs, and ramps.

    Project Details
    • Location: 160 Antioch Pike
    • Total project square footage: 2,712 SF
    • Allocated funding: $2,200,000
    • Architect: Adkisson & Associates Architects
    • Contractor: Dowdle Construction Group
    • Anticipated completion date: August 2017
    • Construction Updates

 

 


  • Hume-Fogg Academic Magnet High School

    Facility Renovation

    This is a complete facility renovation of the existing school. The new design will be in keeping with the design guidelines of the Downtown Historic Commission. The existing hardwood floors and plaster ceilings will be kept intact as much as possible in the new design. Where original windows remain, they will be replaced with new energy efficient windows that are in keeping with the original design aesthetic. This project as includes new lighting, technology infrastructure and new electrical, plumbing and HVAC.

    Project Details
    • Location: 700 Broadway
    • Total project square footage: 201,286 SF
    • Allocated funding: $23,000,000
    • Architect: Kline Swinney Associates
    • Contractor: Messer Construction
    • Anticipated completion date: December 2017
    • Construction Updates

 

 


  • Martin Luther King Jr. Magnet High School

    Addition and Renovation - Phase 2

    This is phase II of the renovation and expansion of MLK. The project will include expansion of the cafeteria, kitchen, and adjacent commons area. The athletic locker rooms will be expanded and the music program will be provided a new home. The project will also renovate most of the existing school to upgrade the existing HVAC, plumbing, and electrical systems.

    Project Details
    • Location: 613 17th Avenue North
    • Total project square footage: 203,731 SF
    • Allocated funding: $30,000,000
    • Architect: Bauer Askew Architecture
    • Contractor: American Constructor
    • Anticipated completion date: December 2018
    • Construction Updates

 

 


  • McMurray Middle School

    Facility Renovation

    This project will be a complete facility modernization including updated HVAC, electrical, plumbing, and complete finishes throughout. The building will also be reorganized for better flow and efficient use of space. There is a small addition planned to allow for the expansion of the administration area. 

    Project Details
    • Location: 520 McMurray Drive
    • Total project square footage: 125,771 SF
    • Allocated funding: $20,750,000
    • Architect: HMK Architects
    • Contractor: Orion Building Corportation
    • Anticipated completion date: May 2019
    • Construction Updates

 

 


  • Overton High School

    Classroom Addition & Facility Renovation

    This project is a complete facility renovation and classroom addition. The building will be modernized and receive new windows, HVAC system, and lighting. The cafeteria will be expanded along with the library and administrative areas. The construction will be phased.

    Project Details
    • Location: 4820 Franklin Pike
    • Total project square footage: 298,185 SF
    • Allocated funding: $40,000,000
    • Architect: TM Partners
    • Contractor: American Constructors
    • Anticipated completion date: July 2018
    • Construction Updates

 

 


  • Pennington Elementary School

    Facility Renovation

    This project is the second phase of work at Pennington Elementary School. Following the addition of classrooms to the school, the remainder of the school will be renovated. The facility renovation will include new HVAC, upgraded electrical and plumbing, new windows, and new finishes throughout.

    Project Details
    • Location: 2817 Donna Hill Drive map it
    • Total project square footage: 45,114 SF
    • Allocated funding: $8,100,100
    • Architect: Melvin Gill & Associates
    • Contractor: Kerry G Campbell, Inc.
    • Anticipated completion date: August 2018
    • Construction Updates

 

 


  • Rosebank Elementary School

    Facility Renovation

    This project is a complete facility renovation. The building will be modernized and receive new windows, HVAC system, and lighting. The cafeteria will be expanded along with the kitchen. The library will be expanded and modernized, as well.

    Project Details
    • Location: 1012 Preston Drive map it
    • Total project square footage: 65,898 SF
    • Allocated funding: $6,000,000
    • Architect: Centric Architecture
    • Contractor: Carden Company
    • Anticipated completion date: January 2018
    • Construction Updates

 

 


  • Antioch Middle School

    Facility Renovation and Addition

    This facility renovation included new HVAC, plumbing, and electrical, new windows and new finishes through the existing building. Two new additions were built to connect the three existing buildings on campus. A new main entrance was constructed on the East side of the building, opposite of the former entrance off Blue Hole Road. Finally, an addition was constructed on the South end of the building to house a new kitchen.

    Project Details
    • Location: 5050 Blue Hole Road
    • Total project square footage: 132,000 SF
    • Allocated funding: $11,000,000
    • Architect: HMK Architects
    • Contractor: RG Anderson Company

 

 


  • Cambridge Early Learning Center

    Building Renovation and Addition

    This project will transform the old Nashville Southeast Branch Library building into a new Early Learning Center. The new space is planned to accommodate 160 new pre-Kindergarten students in the area. For information about how to apply for a seat in the new center, please visit the MNPS early learning website.

    Project Details
    • Location: 2325 Hickory Highlands Drive
    • Total project square footage: 13,344 SF
    • Allocated funding: $2,000,000
    • Architect: Allard Ward Architects
    • Contractor: Dowdle Construction Group
    • Anticipated completion date: August 2016
    • Construction Updates

 

 


  • Glencliff Elementary School

    Classroom Addition

    This project is primarily comprised of a 12 classroom addition, but also includes improvements to the existing cafeteria serving area and the library. The library renovation includes filling in the recessed area in the middle of the space and expanding it to take over some adjacent corridor space. The serving lines in the cafeteria will be reconfigured so that two lines can quickly circulate through the line.

    Project Details
    • Location: 120 Antioch Pike
    • Total project square footage: 16,820 SF
    • Allocated funding: $3,000,000
    • Architect: Bootstrap Architecture
    • Contractor: RG Anderson Company
    • Anticipated completion date: July 2016

 

 


  • Goodlettsville Middle School

    Replacement School

    This is a replacement middle school on the site of the existing school which has been torn down. The students who previously attended Goodlettsville Middle School are currently at Dalewood Middle School until the campus improvements are completed. The new building is three-stories with an internal atrium space with views to all three levels. This school has been designed to achieve LEED silver accreditation once completed.

    Project Details
    • Location: 1460 McGavock Pike
    • Total project square footage: 131,150 SF
    • Allocated funding: $20,176,000
    • Architect: ARTifice Architecture & Gresham Smith and Partners
    • Contractor: Hardaway Construction Company
    • Anticipated completion date: July 2016

 

 


  • Goodlettsville Middle School

    Classroom Addition

    This project includes four additions to the school building. The first is a 4 room addition which includes two classrooms and 2 music rooms. The second is a 6 classroom addition and it connects the central pod to the South classroom wing. The third addition includes two classrooms and connects the central pod to the North classroom wing. The final addition to the school is at the cafeteria and will allow for additional seating. This project also includes a new fire alarm system throughout the building and a new roof for the central pod.

    Project Details
    • Location: 5501 Hill Road
    • Total project square footage: 16,447 SF
    • Allocated funding: $3,079,000
    • Architect: Adkisson Associates Architects, Inc.
    • Contractor: Orion Building Corporation
    • Anticipated completion date: March 2015

     

 

 


  • Henry Maxwell Elementary School

    Classroom Addition

    This is a 13 classroom addition to the existing school building. The new space will allow for the portables on site to be removed and move all the first grade classes into the building. The addition will also allow for an additional 4th grade classroom to be added to the school program.

    Project Details
    • Location: 5535 Blue Hole Road
    • Total project square footage: 17,036 SF
    • Allocated funding: $3,079,000
    • Architect: Melvin Gill & Associates
    • Contractor: Bomar Construction Company
    • Anticipated completion date: April 2015

 

 


  • Henry Oliver Middle School

    Classroom Addition

    The addition to Oliver Middle Prep was mainly comprised of a 9 classroom addition. The addition also included space for a performing arts studio. The final space accommodated by addition to the school was the administrative suite which saw an expansion in this project, as well.

    Project Details
    • Location: 6211 Nolensville Pike
    • Total project square footage: 22,411 SF
    • Allocated funding: $3,700,000
    • Architect: Jack Freeman & Associates
    • Contractor: RG Anderson Company
    • Anticipated completion date: August 2014

 

 


  • Hume-Fogg Academic Magnet High School

    Gymnasium Addition

    This project is a gymnasium addition to the existing school building which includes parking underneath. This gym addition project will offer Hume-Fogg High School the ability to play home basketball games on their campus for the first time in many years. The new space will include a ticket booth, concession stand, and home and away bleachers to seat roughly 1600. The courts will be lighted with state of the art LED light fixtures and controls.

    Project Details
    • Location: 700 Broadway map it
    • Total project square footage: 33,365 SF
    • Allocated funding: $7,900,000
    • Architect: Kline Swinney Associates
    • Contractor: D.F. Chase, Inc
    • Anticipated completion date: August 2015

     

 

 


  • Joelton Middle School

    Facility Renovation & Addition

    This project was primarily comprised of a total facility renovation including all new HVAC, plumbing and electrical systems as well as new finishes throughout. The old gymnasium structure was demolished and an addition for new administrative offices was built and long with additions for a new entry and new classroom space.

    Project Details
    • Location: 3500 Old Clarksville Pike
    • Total project square footage: 87,272 SF
    • Allocated funding: $6,900,000
    • Architect: Edward+Hotchkiss Architects
    • Contractor: Southland Constructors, LLC
    • Completion date: August 2014

 

 


  • John Early Museum Magnet Middle School

    Museum Addition

    This project is an addition to the existing school which includes museum exhibit space, museum storage space, and professional development space. The museum space includes clerestory windows to allow natural light to filter into the space, but maintain ample wall space for exhibits. The spaces in this addition have also been designed for flexible future uses. This project has offered several unique issues with a difficult site due to soil conditions and steep slope.

    Project Details
    • Location: 1000 Cass Street
    • Total project square footage: 5,972 SF
    • Allocated funding: $3,700,000
    • Architect: Moody Nolan
    • Contractor: Carden Company, Inc.
    • Anticipated completion date: July 2015

 

 


  • Madison Middle School

    Classroom Addition

    This project is an addition to the existing school building which will accommodate twelve new classrooms. This expansion project will allow classes in portables on site to be relocated into the building. At the completion of this project, all portables will be removed from the campus.

    Project Details
    • Location: 300 West Old Hickory Boulevard
    • Total project square footage: 17,169 SF
    • Allocated funding: $3,105,000
    • Architect: TMPartners
    • Contractor: Carden Company, Inc.
    • Anticipated completion date: May 2015

 

 


  • Martin Luther King Jr. Magnet High School

    Addition and Renovation - Phase 1

    This addition is a 3 story building planned on the South side of the existing school. The first floor will house an administrative office and new library. The second and third floors will include 5 classrooms each along with additional support spaces. Once the addition is constructed, the old library will be renovated and converted into additional classroom space. This project is the first of two planned phases of expansion for this school.

    Project Details
    • Location: 613 17th Avenue North
    • Total project square footage: 23,742 SF
    • Allocated funding: $6,900,000
    • Architect: Bauer Askew Architecture
    • Contractor: American Constructors
    • Anticipated completion date: May 2017

 

 


  • May Werthan Shayne Elementary School

    Classroom Addition

    This project includes an addition of twelve classrooms and renovation of the existing library area to add an additional classroom. The existing school is single story school on large site and the addition will also be single story. The space added with this project will allow for the portables to be removed from the site when construction is complete. Once the portables are removed, a new playground will be installed where the portables once stood.

    Project Details
    • Location: 6217 Nolensville Pike
    • Total project square footage: 16,048 SF
    • Allocated funding: $3,079,000
    • Architect: Goodwyn Mills Cawood
    • Contractor: Orion Building Corporation
    • Anticipated completion date: May 2015

 

 


  • Norman Binkley Elementary School

    Addition and Renovation

    This project was a total renovation of the existing school building which included new HVAC, plumbing and electrical systems as well as all new finishes throughout. A small addition was also constructed which included a new library and classroom space. The project also included renovation of the existing kitchen.

    Project Details
    • Location: 4700 West Longdale Drive
    • Total project square footage: 67,470 SF
    • Allocated funding: $6,500,000
    • Architect: Street Dixon Rick Architecture
    • Contractor: Orion Building Corporation
    • Anticipated completion date: August 2014